Phase One: Framing Rough Clean:
Remove all wood debris from the interior, exterior perimeter, and in the unit’s courtyard. Stack all lumber in front of each house to be placed in the dumpster. Sweep for framing inspection after electricians and plumber (one sweep).
Phase Two: Box Out Rough Clean:
Remove all roofing debris, including clay tile, nails, paper, and pallets, from the unit’s perimeter. Finish rough clean (one sweep).
Phase Three: Painting Rough Clean:
Remove all wood debris generated from cabinets and finish carpentry. Remove all ceramic tile and/or marble slab and tile, including boxes, wrappers, etc., from the unit’s interior and exterior.
Sweep the entire interior and exterior of the unit.
Sweep and scrape the entire interior of the unit (not including windows).
Remove all boxes, paper, and debris from the unit’s interior, an outer perimeter, and its courtyard.